VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1 (VicTrack) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $2.7m at 2017-18 Q1, against $1.4m at its baseline: +89%.
Its planned finish is 6 Nov 2017, 16 months later than the 29 Jun 2016 first planned.
Its latest rating is Amber (2017-18 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/53d79719-0c8e-475d-a1fa-cc76b22b27fe, as at 18 May 2026. Licence: CC BY 4.0.
How much does VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1 cost? Its cost is $2.7m at 2017-18 Q1, against $1.4m at its baseline: +89%.
Is VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1 late? Its planned finish is 6 Nov 2017, 16 months later than the 29 Jun 2016 first planned.
What is VicTrack Telecommunications Service Management System (TSMS) Implementation - Phase 1's latest rating? Its latest rating is Amber (2017-18 Q1).