WebSphere Application Platform Refresh (WSV) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $1.2m at 2016-17 Q4, against $0.8m at its baseline: +54%.
Its planned finish is 31 Mar 2017, 5 months later than the 31 Oct 2016 first planned.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: WebSphere Application Platform Refresh. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/4ca01af3-5a25-497d-b379-ff49a9defc18, as at 18 May 2026. Licence: CC BY 4.0.
How much does WebSphere Application Platform Refresh cost? Its cost is $1.2m at 2016-17 Q4, against $0.8m at its baseline: +54%.
Is WebSphere Application Platform Refresh late? Its planned finish is 31 Mar 2017, 5 months later than the 31 Oct 2016 first planned.