Internet Remediation Project (DJR) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $4.2m at 2016-17 Q4, against $4.2m at its baseline: no change.
Its planned finish is 31 Mar 2017, 3 months later than the 31 Dec 2016 first planned.
Its latest rating is Green (2016-17 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Internet Remediation Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/4714c415-0d0f-4703-b62b-fb2aa0e5cd79, as at 18 May 2026. Licence: CC BY 4.0.
How much does Internet Remediation Project cost? Its cost is $4.2m at 2016-17 Q4, against $4.2m at its baseline: no change.
Is Internet Remediation Project late? Its planned finish is 31 Mar 2017, 3 months later than the 31 Dec 2016 first planned.
What is Internet Remediation Project's latest rating? Its latest rating is Green (2016-17 Q4).