Mobile Data for Vehicles Pilot (MFESB) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $2.1m at 2017-18 Q1, against $1.8m at its baseline: +20%.
Its planned finish is 30 Nov 2017, 5 months later than the 30 Jun 2017 first planned.
Its latest rating is Amber (2017-18 Q1), down from Green at 2015-16 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Mobile Data for Vehicles Pilot. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/457bded1-eae5-45fc-9819-1e1e30095198, as at 18 May 2026. Licence: CC BY 4.0.
How much does Mobile Data for Vehicles Pilot cost? Its cost is $2.1m at 2017-18 Q1, against $1.8m at its baseline: +20%.
Is Mobile Data for Vehicles Pilot late? Its planned finish is 30 Nov 2017, 5 months later than the 30 Jun 2017 first planned.
What is Mobile Data for Vehicles Pilot's latest rating? Its latest rating is Amber (2017-18 Q1), down from Green at 2015-16 Q3.