Victorian Comprehensive Cancer Centre (VCCC) - ICT Project (DHHS) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $36m at 2015-16 Q4, against $44m at its baseline: -20%.
Its planned finish is 14 Jun 2016, 4 months earlier than the 30 Sep 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Victorian Comprehensive Cancer Centre (VCCC) - ICT Project. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/3cc5c166-8413-4245-a332-47586ec0905e, as at 18 May 2026. Licence: CC BY 4.0.
How much does Victorian Comprehensive Cancer Centre (VCCC) - ICT Project cost? Its cost is $36m at 2015-16 Q4, against $44m at its baseline: -20%.
Is Victorian Comprehensive Cancer Centre (VCCC) - ICT Project late? Its planned finish is 14 Jun 2016, 4 months earlier than the 30 Sep 2016 first planned.
What is Victorian Comprehensive Cancer Centre (VCCC) - ICT Project's latest rating? Its latest rating is Green (2015-16 Q4).