Q04341 - BACID phase 2 (MW) appears in 2 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2015-16 Q4.
Its cost is $1.7m at 2015-16 Q4, against $2.9m at its baseline: -40%.
Its planned finish is 29 Feb 2016, unchanged from the 25 Feb 2016 first planned.
Its latest rating is Green (2015-16 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q04341 - BACID phase 2. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/319480dd-e9ba-4aa0-a15d-2678c55bf08c, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q04341 - BACID phase 2 cost? Its cost is $1.7m at 2015-16 Q4, against $2.9m at its baseline: -40%.
Is Q04341 - BACID phase 2 late? Its planned finish is 29 Feb 2016, unchanged from the 25 Feb 2016 first planned.
What is Q04341 - BACID phase 2's latest rating? Its latest rating is Green (2015-16 Q4).