DJR Information Management Strategy (DJR) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $0.9m at 2016-17 Q4, against $1.4m at its baseline: -33%.
Its planned finish is 30 Jun 2017, 12 months earlier than the 30 Jun 2018 first planned.
Its latest rating is Green (2016-17 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: DJR Information Management Strategy. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/2417684c-75f3-4f2c-b486-2845b2c69f2e, as at 18 May 2026. Licence: CC BY 4.0.
How much does DJR Information Management Strategy cost? Its cost is $0.9m at 2016-17 Q4, against $1.4m at its baseline: -33%.
Is DJR Information Management Strategy late? Its planned finish is 30 Jun 2017, 12 months earlier than the 30 Jun 2018 first planned.
What is DJR Information Management Strategy's latest rating? Its latest rating is Green (2016-17 Q4).