Rail Industry Only (RIO) - Mobile and Handheld Radio Replacement (PTV) appears in 5 snapshots of the Victorian IT dashboard, from 2016-17 Q1 to 2017-18 Q1.
Its planned finish is 30 Dec 2017, 13 months later than the 7 Dec 2016 first planned.
Its latest rating is Green (2017-18 Q1), up from Red at 2016-17 Q1.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Rail Industry Only (RIO) - Mobile and Handheld Radio Replacement. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/209855d5-316b-4fc8-98c9-0eb3dbf9d212, as at 18 May 2026. Licence: CC BY 4.0.
Is Rail Industry Only (RIO) - Mobile and Handheld Radio Replacement late? Its planned finish is 30 Dec 2017, 13 months later than the 7 Dec 2016 first planned.
What is Rail Industry Only (RIO) - Mobile and Handheld Radio Replacement's latest rating? Its latest rating is Green (2017-18 Q1), up from Red at 2016-17 Q1.