Laboratory Information System (Peter Mac) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $2.5m at 2017-18 Q1, against $1.7m at its baseline: +52%.
Its planned finish is 14 Oct 2017, 8 months later than the 31 Jan 2017 first planned.
Its latest rating is Amber (2017-18 Q1), down from Green at 2015-16 Q3.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Laboratory Information System. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/1efa6ad2-088c-4dc4-a098-741d63c68e65, as at 18 May 2026. Licence: CC BY 4.0.
How much does Laboratory Information System cost? Its cost is $2.5m at 2017-18 Q1, against $1.7m at its baseline: +52%.
Is Laboratory Information System late? Its planned finish is 14 Oct 2017, 8 months later than the 31 Jan 2017 first planned.
What is Laboratory Information System's latest rating? Its latest rating is Amber (2017-18 Q1), down from Green at 2015-16 Q3.