SWARH Accelerated adoption of a Regional E.H.R (SWARH) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its planned finish is 30 Jun 2018, 9 months later than the 21 Sep 2017 first planned.
Its latest rating is Green (2017-18 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: SWARH Accelerated adoption of a Regional E.H.R. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/1a1d78fe-a909-464f-81b7-27eced47ac97, as at 18 May 2026. Licence: CC BY 4.0.
Is SWARH Accelerated adoption of a Regional E.H.R late? Its planned finish is 30 Jun 2018, 9 months later than the 21 Sep 2017 first planned.
What is SWARH Accelerated adoption of a Regional E.H.R's latest rating? Its latest rating is Green (2017-18 Q1).