Q03317 - Enhanced Headworks Model Development (MW) appears in 5 snapshots of the Victorian IT dashboard, from 2016-17 Q1 to 2017-18 Q1.
Its cost is $1.1m at 2017-18 Q1, against $1.2m at its baseline: -5%.
Its planned finish is 29 Dec 2017, 3 months later than the 30 Sep 2017 first planned.
Its latest rating is Green (2017-18 Q1).
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Q03317 - Enhanced Headworks Model Development. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/066cd218-ab3f-4856-9cd9-66b6f82668ce, as at 18 May 2026. Licence: CC BY 4.0.
How much does Q03317 - Enhanced Headworks Model Development cost? Its cost is $1.1m at 2017-18 Q1, against $1.2m at its baseline: -5%.
Is Q03317 - Enhanced Headworks Model Development late? Its planned finish is 29 Dec 2017, 3 months later than the 30 Sep 2017 first planned.
What is Q03317 - Enhanced Headworks Model Development's latest rating? Its latest rating is Green (2017-18 Q1).