Emergency Alert Phase 3 - Delivery (DJR) appears in one Victorian IT dashboard snapshot, 2015-16 Q4.
Its cost is $12m at 2015-16 Q4, against $12m at its baseline: no change.
Its planned finish is 13 Sep 2016, 2 months later than the 25 Jul 2016 first planned.
Its latest rating is Green (2015-16 Q4).