Corporate Reporting Tool Upgrade (DHHS) appears in 6 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2016-17 Q4.
Its cost is $1.0m at 2016-17 Q4, against $1.1m at its baseline: -6%.
Its planned finish is 30 Jun 2017, 12 months later than the 30 Jun 2016 first planned.
Its latest rating is Green (2016-17 Q4).
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Corporate Reporting Tool Upgrade. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/041491ee-bcd4-43e1-84f2-ee08a8273a15, as at 18 May 2026. Licence: CC BY 4.0.
How much does Corporate Reporting Tool Upgrade cost? Its cost is $1.0m at 2016-17 Q4, against $1.1m at its baseline: -6%.
Is Corporate Reporting Tool Upgrade late? Its planned finish is 30 Jun 2017, 12 months later than the 30 Jun 2016 first planned.
What is Corporate Reporting Tool Upgrade's latest rating? Its latest rating is Green (2016-17 Q4).