Operator Payment System Modernisation (PTV) appears in 7 snapshots of the Victorian IT dashboard, from 2015-16 Q3 to 2017-18 Q1.
Its cost is $4.4m at 2017-18 Q1, against $10m at its baseline: -56%.
Its planned finish is 1 Aug 2017, 16 months later than the 30 Mar 2016 first planned.
Its latest rating is Green (2017-18 Q1), up from Amber at 2015-16 Q3.
The source marks it completed.
Cite: Victorian Government (DGS) (2026). Victorian IT Project Dashboard: Operator Payment System Modernisation. Tollgate Data, https://data.tollgatehq.com/projects/vic-itd/0041f85b-f19a-4d4f-9d12-81f36def9c2d, as at 18 May 2026. Licence: CC BY 4.0.
How much does Operator Payment System Modernisation cost? Its cost is $4.4m at 2017-18 Q1, against $10m at its baseline: -56%.
Is Operator Payment System Modernisation late? Its planned finish is 1 Aug 2017, 16 months later than the 30 Mar 2016 first planned.
What is Operator Payment System Modernisation's latest rating? Its latest rating is Green (2017-18 Q1), up from Amber at 2015-16 Q3.