Youth Justice Reform Programme (MOJ) appears in 3 snapshots of the UK GMPP, from 2019 Sep to 2023 Mar.
Its cost is £659m at 2023 Mar, against £345m at 2019 Sep: +91%.
Its planned finish is 31 Aug 2024, 20 months later than the 31 Dec 2022 first planned.
Its latest rating is Amber (2023 Mar), up from Amber/Red at 2019 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Youth Justice Reform Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/youthjusticereformprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Youth Justice Reform Programme cost? Its cost is £659m at 2023 Mar, against £345m at 2019 Sep: +91%.
Is Youth Justice Reform Programme late? Its planned finish is 31 Aug 2024, 20 months later than the 31 Dec 2022 first planned.
What is Youth Justice Reform Programme's latest rating? Its latest rating is Amber (2023 Mar), up from Amber/Red at 2019 Sep.