UK Government Major Projects Portfolio (GMPP): 60% of 279 projects now cost more than their baseline figure, as at 31 Mar 2026.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP). Tollgate Data, https://data.tollgatehq.com/datasets/uk-gmpp, as at 31 Mar 2026. Licence: OGL v3.
What share of UK GMPP projects cost more than their baseline? 60% of 279 projects now cost more than their baseline figure. UK Government Major Projects Portfolio (GMPP): the cost at the project's first snapshot against the cost at its latest; nominal, no CPI adjustment.
What share of UK GMPP projects finish later than planned? The source reports 49% of 328 projects finishing late. UK Government Major Projects Portfolio (GMPP): calendar months between the completion date at the project's first snapshot and the date at its latest.
How many UK GMPP projects are rated Red? 20% of the 172 projects rated in 2026 Mar were Red. UK Government Major Projects Portfolio (GMPP): status as the source published it at each snapshot.
How long before a UK GMPP project is first downgraded? The 59 projects that were downgraded took a median 24 months to reach Amber/Red or worse. UK Government Major Projects Portfolio (GMPP): months between a project's first rated snapshot and the first one rating it Amber/Red or worse, over the projects rated in at least two snapshots.
Do bigger UK GMPP projects overrun more often? Cost sits above baseline for 52% to 67% of projects across the four size bands. UK Government Major Projects Portfolio (GMPP): share of projects above baseline cost, by quartile of project size. Association, not cause.
How many UK GMPP projects enter and leave each snapshot? 78% of the 734 projects seen before 2026 Mar are absent from it. UK Government Major Projects Portfolio (GMPP): each bar holds the projects continuing from the previous snapshot and those entering at this one, so it is that snapshot's own population.