YOI Education Services Retender (MOJ) appears in 2 snapshots of the UK GMPP, from 2021 Mar to 2023 Mar.
Its cost is £133m at 2023 Mar, against £195m at 2021 Mar: -32%.
Its planned finish is 31 Mar 2023, unchanged from the 31 Mar 2023 first planned.
Its latest rating is Green (2023 Mar), up from Amber/Green at 2021 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): YOI Education Services Retender. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/yoieducationservicesretender, as at 31 Mar 2026. Licence: OGL v3.
How much does YOI Education Services Retender cost? Its cost is £133m at 2023 Mar, against £195m at 2021 Mar: -32%.
Is YOI Education Services Retender late? Its planned finish is 31 Mar 2023, unchanged from the 31 Mar 2023 first planned.
What is YOI Education Services Retender's latest rating? Its latest rating is Green (2023 Mar), up from Amber/Green at 2021 Mar.