Wellingborough New Build Prison (MOJ) appears in 2 snapshots of the UK GMPP, from 2019 Sep to 2021 Mar.
Its cost is £5.5b at 2021 Mar, against £6.3b at 2019 Sep: -12%.
Its planned finish is 14 Jun 2022, unchanged from the 14 Jun 2022 first planned.
Its latest rating is Amber (2021 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Wellingborough New Build Prison. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/wellingboroughnewbuildprison, as at 31 Mar 2026. Licence: OGL v3.
How much does Wellingborough New Build Prison cost? Its cost is £5.5b at 2021 Mar, against £6.3b at 2019 Sep: -12%.
Is Wellingborough New Build Prison late? Its planned finish is 14 Jun 2022, unchanged from the 14 Jun 2022 first planned.
What is Wellingborough New Build Prison's latest rating? Its latest rating is Amber (2021 Mar).