Washington Embassy Refurbishment (FCDO) appears in 4 snapshots of the UK GMPP, from 2018 Sep to 2023 Mar.
Its cost is £122m at 2023 Mar, against £64m at 2018 Sep: +92%.
Its planned finish is 1 Aug 2023, 8 months later than the 12 Dec 2022 first planned.
Its latest rating is Amber (2023 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Washington Embassy Refurbishment. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/washingtonembassyrefurbishment, as at 31 Mar 2026. Licence: OGL v3.
How much does Washington Embassy Refurbishment cost? Its cost is £122m at 2023 Mar, against £64m at 2018 Sep: +92%.
Is Washington Embassy Refurbishment late? Its planned finish is 1 Aug 2023, 8 months later than the 12 Dec 2022 first planned.
What is Washington Embassy Refurbishment's latest rating? Its latest rating is Amber (2023 Mar).