Visitor and Migrant NHS Cost Recovery Programme (DHSC) appears in 3 snapshots of the UK GMPP, from 2016 Sep to 2018 Sep.
Its cost is £33m at 2018 Sep, against £19m at 2016 Sep: +72%.
Its planned finish is 31 Mar 2019, 12 months later than the 31 Mar 2018 first planned.
Its latest rating is Amber/Green (2018 Sep), up from Amber/Red at 2016 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Visitor and Migrant NHS Cost Recovery Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/visitorandmigrantnhscostrecoveryprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Visitor and Migrant NHS Cost Recovery Programme cost? Its cost is £33m at 2018 Sep, against £19m at 2016 Sep: +72%.
Is Visitor and Migrant NHS Cost Recovery Programme late? Its planned finish is 31 Mar 2019, 12 months later than the 31 Mar 2018 first planned.
What is Visitor and Migrant NHS Cost Recovery Programme's latest rating? Its latest rating is Amber/Green (2018 Sep), up from Amber/Red at 2016 Sep.