The Tate Modern Project (DCMS) appears in 3 snapshots of the UK GMPP, from 2012 Sep to 2016 Sep.
Its cost is £271m at 2016 Sep, against £215m at 2012 Sep: +26%.
Its planned finish is 31 Dec 2016, 20 months later than the 1 May 2015 first planned.
Its latest rating is Green (2016 Sep).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): The Tate Modern Project. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/thetatemodernproject, as at 31 Mar 2026. Licence: OGL v3.
How much does The Tate Modern Project cost? Its cost is £271m at 2016 Sep, against £215m at 2012 Sep: +26%.
Is The Tate Modern Project late? Its planned finish is 31 Dec 2016, 20 months later than the 1 May 2015 first planned.
What is The Tate Modern Project's latest rating? Its latest rating is Green (2016 Sep).