SUBMARINE WATERFRONT INFRASTRUCTURE FUTURE (MOD) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its planned finish is 21 May 2031, 43 months later than the 31 Oct 2027 first planned.
Its latest rating is Red (2026 Mar), down from Amber at 2023 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): SUBMARINE WATERFRONT INFRASTRUCTURE FUTURE. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/submarinewaterfrontinfrastructurefuture, as at 31 Mar 2026. Licence: OGL v3.
Is SUBMARINE WATERFRONT INFRASTRUCTURE FUTURE late? Its planned finish is 21 May 2031, 43 months later than the 31 Oct 2027 first planned.
What is SUBMARINE WATERFRONT INFRASTRUCTURE FUTURE's latest rating? Its latest rating is Red (2026 Mar), down from Amber at 2023 Mar.