Spectrum Clearance and Awards Programme (DCMS) appears in 2 snapshots of the UK GMPP, from 2012 Sep to 2013 Sep.
Its cost is £247m at 2013 Sep, against £281m at 2012 Sep: -12%.
Its planned finish is 31 Dec 2014, unchanged from the 31 Dec 2014 first planned.
Its latest rating is Amber/Green (2013 Sep), up from Amber at 2012 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Spectrum Clearance and Awards Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/spectrumclearanceandawardsprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Spectrum Clearance and Awards Programme cost? Its cost is £247m at 2013 Sep, against £281m at 2012 Sep: -12%.
Is Spectrum Clearance and Awards Programme late? Its planned finish is 31 Dec 2014, unchanged from the 31 Dec 2014 first planned.
What is Spectrum Clearance and Awards Programme's latest rating? Its latest rating is Amber/Green (2013 Sep), up from Amber at 2012 Sep.