South West Route Capacity (DFT) appears in 2 snapshots of the UK GMPP, from 2019 Sep to 2021 Mar.
Its cost is £695m at 2021 Mar, against £818m at 2019 Sep: -15%.
Its planned finish is 31 Aug 2021, 20 months later than the 31 Dec 2019 first planned.
Its latest rating is Green (2021 Mar), up from Amber/Green at 2019 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): South West Route Capacity. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/southwestroutecapacity, as at 31 Mar 2026. Licence: OGL v3.
How much does South West Route Capacity cost? Its cost is £695m at 2021 Mar, against £818m at 2019 Sep: -15%.
Is South West Route Capacity late? Its planned finish is 31 Aug 2021, 20 months later than the 31 Dec 2019 first planned.
What is South West Route Capacity's latest rating? Its latest rating is Green (2021 Mar), up from Amber/Green at 2019 Sep.