Smart Meters Implementation Programme (BEIS) appears in 4 snapshots of the UK GMPP, from 2013 Sep to 2016 Sep.
Its cost is £17.2b at 2016 Sep, against £17.2b at 2013 Sep: +0%.
Its planned finish is 31 Dec 2020, 3 months later than the 30 Sep 2020 first planned.
Its latest rating is Amber (2016 Sep).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Smart Meters Implementation Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/smartmetersimplementationprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Smart Meters Implementation Programme cost? Its cost is £17.2b at 2016 Sep, against £17.2b at 2013 Sep: +0%.
Is Smart Meters Implementation Programme late? Its planned finish is 31 Dec 2020, 3 months later than the 30 Sep 2020 first planned.
What is Smart Meters Implementation Programme's latest rating? Its latest rating is Amber (2016 Sep).