SIXEP CONTINUITY PLANT (DESNZ) appears in 4 snapshots of the UK GMPP, from 2021 Mar to 2026 Mar.
Its cost is £1.1b at 2026 Mar, against £590m at 2021 Mar: +86%.
Its planned finish is 21 Oct 2031, 46 months later than the 20 Dec 2027 first planned.
Its latest rating is Green (2026 Mar), up from Amber/Red at 2021 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): SIXEP CONTINUITY PLANT. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/sixepcontinuityplant, as at 31 Mar 2026. Licence: OGL v3.
How much does SIXEP CONTINUITY PLANT cost? Its cost is £1.1b at 2026 Mar, against £590m at 2021 Mar: +86%.
Is SIXEP CONTINUITY PLANT late? Its planned finish is 21 Oct 2031, 46 months later than the 20 Dec 2027 first planned.
What is SIXEP CONTINUITY PLANT's latest rating? Its latest rating is Green (2026 Mar), up from Amber/Red at 2021 Mar.