Sellafield Product and Residue Store Retreatment Plant (DESNZ) appears in 2 snapshots of the UK GMPP, from 2021 Mar to 2023 Mar.
Its cost is £1.4b at 2023 Mar, against £764m at 2021 Mar: +81%.
Its planned finish is 9 Oct 2029, 35 months later than the 2 Nov 2026 first planned.
Its latest rating is Green (2023 Mar), up from Amber/Red at 2021 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Sellafield Product and Residue Store Retreatment Plant. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/sellafieldproductandresiduestoreretreatmentplant, as at 31 Mar 2026. Licence: OGL v3.
How much does Sellafield Product and Residue Store Retreatment Plant cost? Its cost is £1.4b at 2023 Mar, against £764m at 2021 Mar: +81%.
Is Sellafield Product and Residue Store Retreatment Plant late? Its planned finish is 9 Oct 2029, 35 months later than the 2 Nov 2026 first planned.
What is Sellafield Product and Residue Store Retreatment Plant's latest rating? Its latest rating is Green (2023 Mar), up from Amber/Red at 2021 Mar.