Sellafield Model Change (SMC) (BEIS) appears in 4 snapshots of the UK GMPP, from 2015 Sep to 2018 Sep.
Its cost is £30.0b at 2018 Sep, against £30.0b at 2015 Sep: +0%.
Its planned finish is 24 May 2017, unchanged from the 24 May 2017 first planned.
Its latest rating is Green (2018 Sep), up from Amber at 2015 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Sellafield Model Change (SMC). Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/sellafieldmodelchangesmc, as at 31 Mar 2026. Licence: OGL v3.
How much does Sellafield Model Change (SMC) cost? Its cost is £30.0b at 2018 Sep, against £30.0b at 2015 Sep: +0%.
Is Sellafield Model Change (SMC) late? Its planned finish is 24 May 2017, unchanged from the 24 May 2017 first planned.
What is Sellafield Model Change (SMC)'s latest rating? Its latest rating is Green (2018 Sep), up from Amber at 2015 Sep.