Project Gigabit (DSIT) appears in 5 snapshots of the UK GMPP, from 2022 Mar to 2026 Mar.
Its cost is £5.2b at 2026 Mar, against £5.0b at 2022 Mar: +4%.
Its planned finish is 31 Dec 2032, 24 months later than the 31 Dec 2030 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Project Gigabit. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/projectgigabit, as at 31 Mar 2026. Licence: OGL v3.
How much does Project Gigabit cost? Its cost is £5.2b at 2026 Mar, against £5.0b at 2022 Mar: +4%.
Is Project Gigabit late? Its planned finish is 31 Dec 2032, 24 months later than the 31 Dec 2030 first planned.
What is Project Gigabit's latest rating? Its latest rating is Amber (2026 Mar).