Prisoner Education Services (MOJ) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its cost is £1.8b at 2026 Mar, against £1.9b at 2023 Mar: -7%.
Its planned finish is 31 Jan 2027, 19 months later than the 30 Jun 2025 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Prisoner Education Services. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/prisonereducationservices, as at 31 Mar 2026. Licence: OGL v3.
How much does Prisoner Education Services cost? Its cost is £1.8b at 2026 Mar, against £1.9b at 2023 Mar: -7%.
Is Prisoner Education Services late? Its planned finish is 31 Jan 2027, 19 months later than the 30 Jun 2025 first planned.
What is Prisoner Education Services's latest rating? Its latest rating is Amber (2026 Mar).