Priority School Building Programme 2 (DFE) appears in 4 snapshots of the UK GMPP, from 2015 Sep to 2019 Sep.
Its cost is £2.4b at 2019 Sep, against £1.6b at 2015 Sep: +52%.
Its planned finish is 25 Feb 2025, 47 months later than the 31 Mar 2021 first planned.
Its latest rating is Amber (2019 Sep), up from Amber/Red at 2015 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Priority School Building Programme 2. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/priorityschoolbuildingprogramme2, as at 31 Mar 2026. Licence: OGL v3.
How much does Priority School Building Programme 2 cost? Its cost is £2.4b at 2019 Sep, against £1.6b at 2015 Sep: +52%.
Is Priority School Building Programme 2 late? Its planned finish is 25 Feb 2025, 47 months later than the 31 Mar 2021 first planned.
What is Priority School Building Programme 2's latest rating? Its latest rating is Amber (2019 Sep), up from Amber/Red at 2015 Sep.