Open Networks Programme (DSIT) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2025 Mar.
Its cost is £325m at 2025 Mar, against £325m at 2023 Mar: no change.
Its planned finish is 31 Mar 2025, unchanged from the 31 Mar 2025 first planned.
Its latest rating is Green (2025 Mar), up from Amber at 2023 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Open Networks Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/opennetworksprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Open Networks Programme cost? Its cost is £325m at 2025 Mar, against £325m at 2023 Mar: no change.
Is Open Networks Programme late? Its planned finish is 31 Mar 2025, unchanged from the 31 Mar 2025 first planned.
What is Open Networks Programme's latest rating? Its latest rating is Green (2025 Mar), up from Amber at 2023 Mar.