Nuclear Warhead Capability Sustainment Programme (MOD) appears in 3 snapshots of the UK GMPP, from 2012 Sep to 2017 Sep.
Its cost is £19.9b at 2017 Sep, against £12.1b at 2012 Sep: +64%.
Its planned finish is 30 Apr 2025, unchanged from the 30 Apr 2025 first planned.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Nuclear Warhead Capability Sustainment Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/nuclearwarheadcapabilitysustainmentprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Nuclear Warhead Capability Sustainment Programme cost? Its cost is £19.9b at 2017 Sep, against £12.1b at 2012 Sep: +64%.
Is Nuclear Warhead Capability Sustainment Programme late? Its planned finish is 30 Apr 2025, unchanged from the 30 Apr 2025 first planned.