National Proton Beam Therapy (PBT) Service Development Programme (DHSC) appears in 5 snapshots of the UK GMPP, from 2016 Sep to 2021 Mar.
Its cost is £1.2b at 2021 Mar, against £1.2b at 2016 Sep: -0%.
Its planned finish is 30 May 2018, unchanged from the 30 May 2018 first planned.
Its latest rating is Green (2021 Mar), up from Amber at 2016 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): National Proton Beam Therapy (PBT) Service Development Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/nationalprotonbeamtherapypbtservicedevelopmentprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does National Proton Beam Therapy (PBT) Service Development Programme cost? Its cost is £1.2b at 2021 Mar, against £1.2b at 2016 Sep: -0%.
Is National Proton Beam Therapy (PBT) Service Development Programme late? Its planned finish is 30 May 2018, unchanged from the 30 May 2018 first planned.
What is National Proton Beam Therapy (PBT) Service Development Programme's latest rating? Its latest rating is Green (2021 Mar), up from Amber at 2016 Sep.