MIDLANDS RAIL HUB (DFT) appears in 5 snapshots of the UK GMPP, from 2021 Mar to 2026 Mar.
Its cost is £948m at 2026 Mar, against £1.6b at 2021 Mar: -39%.
Its planned finish is 31 Dec 2040, 90 months later than the 30 Jun 2033 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): MIDLANDS RAIL HUB. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/midlandsrailhub, as at 31 Mar 2026. Licence: OGL v3.
How much does MIDLANDS RAIL HUB cost? Its cost is £948m at 2026 Mar, against £1.6b at 2021 Mar: -39%.
Is MIDLANDS RAIL HUB late? Its planned finish is 31 Dec 2040, 90 months later than the 30 Jun 2033 first planned.
What is MIDLANDS RAIL HUB's latest rating? Its latest rating is Amber (2026 Mar).