Midland Main Line Programme (DFT) appears in 4 snapshots of the UK GMPP, from 2019 Sep to 2024 Mar.
Its cost is £1.4b at 2024 Mar, against £1.7b at 2019 Sep: -15%.
Its planned finish is 31 Dec 2024, unchanged from the 31 Dec 2024 first planned.
Its latest rating is Green (2024 Mar), up from Amber at 2019 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Midland Main Line Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/midlandmainlineprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Midland Main Line Programme cost? Its cost is £1.4b at 2024 Mar, against £1.7b at 2019 Sep: -15%.
Is Midland Main Line Programme late? Its planned finish is 31 Dec 2024, unchanged from the 31 Dec 2024 first planned.
What is Midland Main Line Programme's latest rating? Its latest rating is Green (2024 Mar), up from Amber at 2019 Sep.