LOWER THAMES CROSSING (DFT) appears in 6 snapshots of the UK GMPP, from 2019 Sep to 2026 Mar.
Its cost is £9.9b at 2026 Mar, against £6.1b at 2019 Sep: +64%.
Its planned finish is 31 Jul 2035, 84 months later than the 31 Jul 2028 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): LOWER THAMES CROSSING. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/lowerthamescrossing, as at 31 Mar 2026. Licence: OGL v3.
How much does LOWER THAMES CROSSING cost? Its cost is £9.9b at 2026 Mar, against £6.1b at 2019 Sep: +64%.
Is LOWER THAMES CROSSING late? Its planned finish is 31 Jul 2035, 84 months later than the 31 Jul 2028 first planned.
What is LOWER THAMES CROSSING's latest rating? Its latest rating is Amber (2026 Mar).