Levelling Up Home Building Fund (MHCLG) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its cost is £2.0b at 2026 Mar, against £2.2b at 2023 Mar: -10%.
Its planned finish is 31 Mar 2032, 12 months later than the 31 Mar 2031 first planned.
Its latest rating is Green (2026 Mar), up from Amber at 2023 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Levelling Up Home Building Fund. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/levellinguphomebuildingfund, as at 31 Mar 2026. Licence: OGL v3.
How much does Levelling Up Home Building Fund cost? Its cost is £2.0b at 2026 Mar, against £2.2b at 2023 Mar: -10%.
Is Levelling Up Home Building Fund late? Its planned finish is 31 Mar 2032, 12 months later than the 31 Mar 2031 first planned.
What is Levelling Up Home Building Fund's latest rating? Its latest rating is Green (2026 Mar), up from Amber at 2023 Mar.