Levelling Up Fund (MHCLG) appears in 3 snapshots of the UK GMPP, from 2022 Mar to 2025 Mar.
Its cost is £4.8b at 2025 Mar, against £4.8b at 2022 Mar: -0%.
Its planned finish is 31 Mar 2028, 24 months later than the 31 Mar 2026 first planned.
Its latest rating is Amber (2025 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Levelling Up Fund. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/levellingupfund, as at 31 Mar 2026. Licence: OGL v3.
How much does Levelling Up Fund cost? Its cost is £4.8b at 2025 Mar, against £4.8b at 2022 Mar: -0%.
Is Levelling Up Fund late? Its planned finish is 31 Mar 2028, 24 months later than the 31 Mar 2026 first planned.
What is Levelling Up Fund's latest rating? Its latest rating is Amber (2025 Mar).