LAND INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE (ISTAR) (MOD) appears in 3 snapshots of the UK GMPP, from 2023 Mar to 2026 Mar.
Its cost is £1.5b at 2026 Mar, against £1.6b at 2023 Mar: -6%.
Its planned finish is 2 May 2033, 64 months later than the 31 Dec 2027 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): LAND INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE (ISTAR). Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/landintelligencesurveillancetargetacquisitionandreconnaissanceistar, as at 31 Mar 2026. Licence: OGL v3.
How much does LAND INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE (ISTAR) cost? Its cost is £1.5b at 2026 Mar, against £1.6b at 2023 Mar: -6%.
Is LAND INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE (ISTAR) late? Its planned finish is 2 May 2033, 64 months later than the 31 Dec 2027 first planned.
What is LAND INTELLIGENCE, SURVEILLANCE, TARGET ACQUISITION AND RECONNAISSANCE (ISTAR)'s latest rating? Its latest rating is Amber (2026 Mar).