JAKARTA: New Embassy appears in 2 snapshots of the UK GMPP, from 2012 Sep to 2013 Sep.
Its cost is £29m at 2013 Sep, against £29m at 2012 Sep: +2%.
Its planned finish is 9 Jan 2014, 8 months earlier than the 1 Sep 2014 first planned.
Its latest rating is Amber/Green (2013 Sep).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): JAKARTA: New Embassy. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/jakartanewembassy, as at 31 Mar 2026. Licence: OGL v3.
How much does JAKARTA: New Embassy cost? Its cost is £29m at 2013 Sep, against £29m at 2012 Sep: +2%.
Is JAKARTA: New Embassy late? Its planned finish is 9 Jan 2014, 8 months earlier than the 1 Sep 2014 first planned.
What is JAKARTA: New Embassy's latest rating? Its latest rating is Amber/Green (2013 Sep).