IT Infrastructure Sourcing Programme (DHSC) appears in 3 snapshots of the UK GMPP, from 2017 Sep to 2019 Sep.
Its cost is £121m at 2019 Sep, against £127m at 2017 Sep: -4%.
Its planned finish is 30 Jun 2019, unchanged from the 30 Jun 2019 first planned.
Its latest rating is Red (2019 Sep), down from Amber/Red at 2017 Sep.