ICR Monetisation (DFE) appears in 3 snapshots of the UK GMPP, from 2013 Sep to 2016 Sep.
Its cost is £15m at 2016 Sep, against £29m at 2013 Sep: -47%.
Its planned finish is 31 Mar 2017, 21 months earlier than the 31 Dec 2018 first planned.
Its latest rating is Amber (2016 Sep), up from Amber/Red at 2013 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): ICR Monetisation. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/icrmonetisation, as at 31 Mar 2026. Licence: OGL v3.
How much does ICR Monetisation cost? Its cost is £15m at 2016 Sep, against £29m at 2013 Sep: -47%.
Is ICR Monetisation late? Its planned finish is 31 Mar 2017, 21 months earlier than the 31 Dec 2018 first planned.
What is ICR Monetisation's latest rating? Its latest rating is Amber (2016 Sep), up from Amber/Red at 2013 Sep.