Hydrogen Allocation Round 1 (HAR1) (DESNZ) appears in 2 snapshots of the UK GMPP, from 2025 Mar to 2026 Mar.
Its cost is £2.5b at 2026 Mar, against £2.4b at 2025 Mar: +4%.
Its planned finish is 30 Jun 2042, unchanged from the 30 Jun 2042 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Hydrogen Allocation Round 1 (HAR1). Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/hydrogenallocationround1har1, as at 31 Mar 2026. Licence: OGL v3.
How much does Hydrogen Allocation Round 1 (HAR1) cost? Its cost is £2.5b at 2026 Mar, against £2.4b at 2025 Mar: +4%.
Is Hydrogen Allocation Round 1 (HAR1) late? Its planned finish is 30 Jun 2042, unchanged from the 30 Jun 2042 first planned.
What is Hydrogen Allocation Round 1 (HAR1)'s latest rating? Its latest rating is Amber (2026 Mar).