HOUSING INFRASTRUCTURE FUND (MHCLG) appears in 5 snapshots of the UK GMPP, from 2021 Mar to 2026 Mar.
Its cost is £4.3b at 2026 Mar, against £4.4b at 2021 Mar: -3%.
Its planned finish is 31 Mar 2028, unchanged from the 31 Mar 2028 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): HOUSING INFRASTRUCTURE FUND. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/housinginfrastructurefund, as at 31 Mar 2026. Licence: OGL v3.
How much does HOUSING INFRASTRUCTURE FUND cost? Its cost is £4.3b at 2026 Mar, against £4.4b at 2021 Mar: -3%.
Is HOUSING INFRASTRUCTURE FUND late? Its planned finish is 31 Mar 2028, unchanged from the 31 Mar 2028 first planned.
What is HOUSING INFRASTRUCTURE FUND's latest rating? Its latest rating is Amber (2026 Mar).