HMRC NORTHERN IRELAND DELIVERY PROGRAMME (HMRC) appears in 2 snapshots of the UK GMPP, from 2025 Mar to 2026 Mar.
Its cost is £713m at 2026 Mar, against £573m at 2025 Mar: +24%.
Its planned finish is 31 Mar 2027, unchanged from the 31 Mar 2027 first planned.
Its latest rating is Amber (2026 Mar).
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): HMRC NORTHERN IRELAND DELIVERY PROGRAMME. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/hmrcnorthernirelanddeliveryprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does HMRC NORTHERN IRELAND DELIVERY PROGRAMME cost? Its cost is £713m at 2026 Mar, against £573m at 2025 Mar: +24%.
Is HMRC NORTHERN IRELAND DELIVERY PROGRAMME late? Its planned finish is 31 Mar 2027, unchanged from the 31 Mar 2027 first planned.
What is HMRC NORTHERN IRELAND DELIVERY PROGRAMME's latest rating? Its latest rating is Amber (2026 Mar).