Great Western Route Modernisation (GWRM) including electrification (DFT) appears in 2 snapshots of the UK GMPP, from 2019 Sep to 2021 Mar.
Its cost is £5.2b at 2021 Mar, against £5.0b at 2019 Sep: +3%.
Its planned finish is 31 Dec 2024, unchanged from the 31 Dec 2024 first planned.
Its latest rating is Green (2021 Mar), up from Amber at 2019 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Great Western Route Modernisation (GWRM) including electrification. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/greatwesternroutemodernisationgwrmincludingelectrification, as at 31 Mar 2026. Licence: OGL v3.
How much does Great Western Route Modernisation (GWRM) including electrification cost? Its cost is £5.2b at 2021 Mar, against £5.0b at 2019 Sep: +3%.
Is Great Western Route Modernisation (GWRM) including electrification late? Its planned finish is 31 Dec 2024, unchanged from the 31 Dec 2024 first planned.
What is Great Western Route Modernisation (GWRM) including electrification's latest rating? Its latest rating is Green (2021 Mar), up from Amber at 2019 Sep.