Government Office Hubs Programme (CO) appears in 2 snapshots of the UK GMPP, from 2015 Sep to 2016 Sep.
Its cost is £1.1b at 2016 Sep, against £42m at 2015 Sep: +2464%.
Its planned finish is 31 Dec 2021, 24 months earlier than the 31 Dec 2023 first planned.
Its latest rating is Amber (2016 Sep), up from Amber/Red at 2015 Sep.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Government Office Hubs Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/governmentofficehubsprogramme, as at 31 Mar 2026. Licence: OGL v3.
How much does Government Office Hubs Programme cost? Its cost is £1.1b at 2016 Sep, against £42m at 2015 Sep: +2464%.
Is Government Office Hubs Programme late? Its planned finish is 31 Dec 2021, 24 months earlier than the 31 Dec 2023 first planned.
What is Government Office Hubs Programme's latest rating? Its latest rating is Amber (2016 Sep), up from Amber/Red at 2015 Sep.