FUTURE SUPPLIERS SERVICES (HO) appears in 5 snapshots of the UK GMPP, from 2021 Mar to 2025 Mar.
Its cost is £529m at 2025 Mar, against £928m at 2021 Mar: -43%.
Its planned finish is 30 May 2025, 13 months later than the 1 May 2024 first planned.
Its latest rating is Green (2025 Mar), up from Amber/Red at 2021 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): FUTURE SUPPLIERS SERVICES. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/futuresuppliersservices, as at 31 Mar 2026. Licence: OGL v3.
How much does FUTURE SUPPLIERS SERVICES cost? Its cost is £529m at 2025 Mar, against £928m at 2021 Mar: -43%.
Is FUTURE SUPPLIERS SERVICES late? Its planned finish is 30 May 2025, 13 months later than the 1 May 2024 first planned.
What is FUTURE SUPPLIERS SERVICES's latest rating? Its latest rating is Green (2025 Mar), up from Amber/Red at 2021 Mar.