Future NHS Workforce Solution Transformation Programme (DHSC) appears in 2 snapshots of the UK GMPP, from 2025 Mar to 2026 Mar.
Its planned finish is 28 Feb 2031, 1 months later than the 31 Jan 2031 first planned.
Its latest rating is Amber (2026 Mar), down from Green at 2025 Mar.
Cite: IPA / NISTA (Cabinet Office) (2026). UK Government Major Projects Portfolio (GMPP): Future NHS Workforce Solution Transformation Programme. Tollgate Data, https://data.tollgatehq.com/projects/uk-gmpp/futurenhsworkforcesolutiontransformationprogramme, as at 31 Mar 2026. Licence: OGL v3.
Is Future NHS Workforce Solution Transformation Programme late? Its planned finish is 28 Feb 2031, 1 months later than the 31 Jan 2031 first planned.
What is Future NHS Workforce Solution Transformation Programme's latest rating? Its latest rating is Amber (2026 Mar), down from Green at 2025 Mar.